A dozen permissions, eight authorities, and one register.

A working plant carries far more paper than the factory licence. Each permission sits with a different authority, renews on its own clock, and is usually remembered by a different person. The register below is the common case; the site assessment establishes what a particular plant actually carries, and what on it has already lapsed.

Physician and safety engineer Two-week assessment Every register, obligation by obligation No obligation

What the gate depends on

The register

Eight authorities, each with its own form, its own fee and its own clock.

Authority or statuteWhat it grantsWhy it lapses
Factories Act, 1948Factory licence, plan approval and annual renewalRenewal treated as routine until a plan change makes it anything but
Water and Air ActsConsent to Establish and Consent to OperateCapacity or product mix changed without amending the consent
State Fire ServiceFire NOC and fire-fighting scheme approvalRenewal needs a revised fire-load drawing nobody has kept
Boilers ActBoiler registration, inspection and renewalInspection date missed while the boiler stays in service
PESOPetroleum, compressed gas and explosives licencesStorage quantity crept past what the licence permits
Electrical InspectorateInstallation approval and safety certificateAdditions made to the installation after the certificate was issued
Contract Labour Act, 1970Principal employer registration and contractor licencesA new contractor engaged without a licence in his own name
BOCW Act, 1996Registration and cess, wherever the site buildsConstruction begun before registration, cess computed late
Legal MetrologyWeighbridge and instrument verificationStamping expired on an instrument still being used commercially

How the register is kept

Statura’s part

Established, not assumed
The assessment reads what the site actually holds, against what its process, headcount and classification require. Plants are routinely surprised in both directions.
A date and an owner on every line
Each permission carries its expiry, its lead time, and the name of the person answerable — ours, or yours by agreement. A register with no owner is a list.
Filed a month ahead
Renewals are lodged thirty days before expiry, so a query or a rejection still leaves room to correct and refile before the permission dies.
Notices answered the same day
Correspondence from an inspectorate or a Board is acknowledged on the working day it arrives, with the reply drafted and dated rather than left to accumulate.
Evidence, not assertion
The acknowledgement is kept, not just the claim that a thing was filed. What matters during an inspection is what can be produced in minutes.

What we do not hold ourselves

An honest boundary

No single firm holds specialist competence in every one of these. What Statura commits to is that the obligation does not come back to you unresolved: where a specialist is needed, that specialist is engaged under our contract, managed by us and invoiced through us. You do not acquire a second vendor to manage.

In-house
Factory, health, safety and environmental filings; audits; the register itself; drawings and fabrication.
Engaged under our contract
Specialist statutory work such as chartered structural certification, accredited laboratory testing, and authority-specific technical submissions.
Never handed back
The line stays on our register with our name against it either way. That is the whole point of a single operator.

Questions

Can Statura obtain a licence we have never held?

Yes. New applications are a larger piece of work than renewals because they usually require drawings, technical submissions and a site inspection, but they are the same kind of work. The assessment establishes what is missing before anything is quoted.

What happens to a permission that has already lapsed?

It is triaged by consequence rather than by date. A lapsed consent or fire NOC is treated ahead of a lapsed instrument verification, because the first can stop the plant and the second cannot. The exposure is stated honestly, including where a penalty is likely.

Do you replace our existing consultant?

Not necessarily, and there is no advantage in pretending otherwise. Where a consultant is doing a specialist piece well, they can be engaged under our contract so that the accountability still sits in one place. What we will not do is leave you coordinating between us.

Is this separate from the safety and health service?

It is the same contract and the same register. The divisions describe how the work is staffed, not how it is bought.

Related

Elsewhere on this site

Start with one site.

Send us one site. A physician and an industrial safety engineer walk it over two weeks and hand back a written report: the statutory obligations that apply, where the current arrangement falls short, the staffing and equipment required, and a recommended operating model. No charge, no obligation, and the report is yours to keep either way.

Medical assistance
+91 95383 71985
+91 81688 67102
Enquiries
prabhat@statura.co.in
Entity
Statura Health LLP
Industrial sites across India